Transfer of the external electrical load from the WAPDA supply to a single MES metering point.

ClientMES LahoreLocationLahoreDate of Award06.05.2014Year2014StatusCompletedShare

Transfer of the external electrical load from the WAPDA supply to a single Military Engineering Services metering point.

Works included re-routing of feeders, modification of the distribution arrangement, protection co-ordination for the new configuration, and testing and commissioning of the one-point connection with minimal interruption to supply.